Jun 07 2019

Case Study: Slick-O-Line Service Delivers Leak Investigation - Tubing Leak


+ Intervention Technologies


Overview

A UKCS Operator was observing Tubing to A-Annulus communication. They needed to determine the source of the communication to enable remediation, in turn protecting 1.5mboed through barrier compliant operations.

Challenge

The requirement to identify the source of communication quickly and ensure the wellbeing of the entire wellbore was critical to the operation due to enforced operational time constraints as part of a campaign of intervention work on an NUI.

Solution

A retro-fit Slick-O-Line™ package was mobilised to the platform pre-mounted on a slickline winch to perform a distributed fibre optic survey. The Paradigm Slick-O-Line™ service had been chosen due to its reduced intervention and survey time, quick turnaround of data and ability to survey the entire well simultaneously.

Result

  • Acoustic and Temperature responses were detected over a specific interval allowing the identification of the point of communication between Tubing and A-annulus.
  • No other issues were observed in the well.
  • It took 15 hours to complete the intervention.
  • Data was processed and interpreted within 12 hours of acquisition.
  • Regular pressure control equipment and procedures were applied saving time and cost.
  • In addition to the Temperature and Acoustic fibre survey memory GR, temperature and pressure data were also gathered providing a more comprehensive surveillance package in the well.

Download Full Case Study

Download Full Case Study

Please login with your email address to access this file.

If you do not have already have an account, please fill in the registration form to create one.

You will be required to verify your email address to activate your account. Please check your spam mailbox if a verification email does not arrive imminently.

Quick Contact
Back to top

/case-studies/case-study-slick-o-line-service-delivers-leak-investigation-tubing-leak